This is the sequence every project runs through, from first email to loaded container. It is the same whether you are ordering a single villa or a full hotel floor — only the volume and the number of approval steps change.
Knowing it in advance is the difference between a project that lands on the site date and one that slips a month because a sample was rejected late or a specification was changed after production released.
You send dimensioned drawings or layouts, a finish schedule or reference images, quantities per item by room, the destination market, and the required on-site date. If the drawings are incomplete that is normal at this stage; we will tell you what is missing rather than quote around the gaps.
What we check: whether each detail is buildable as drawn, whether any dimension conflicts with the stated material thickness, and whether the finish specified is achievable against the budget implied.
Within 48 hours of a complete package we return a line-by-line quotation. Each line states the substrate, the surface, the hardware grade and the unit price, so that a competing quote can be compared like for like instead of on a single total.
Where a line is ambiguous we will quote the assumption explicitly, so you can see exactly what has been priced.
Depending on the project this is a finish panel, a single door, a drawer box, or a full sample room. The purpose is the same in every case: to approve a physical piece before anything goes to bulk.
Why this matters:
Renderings and screen colours lie. A veneer that reads warm on a monitor can go grey under a hotel corridor’s lighting. Approving the sample is the only point where that is cheap to fix.
On villa and flat projects, production is released against a measured survey rather than the architect’s drawing set, because walls are rarely built exactly to plan. On hotel work this step is usually replaced by a shop drawing review with the contractor.
Once the sample is signed off and the deposit confirmed, the job is scheduled into the line. At this point the specification is frozen. Changes after release mean re-cutting and re-finishing, and they are priced as such — which is why it is worth spending the time at step 3.
Panels are cut on CNC against the released drawing set, edges banded — laser or PUR depending on the finish and the humidity of the destination — assembled, then sanded and finished. Wet-area components are built from ENF-grade multilayer plywood; dry storage may use moisture-resistant particle board where the budget calls for it.
Three checkpoints, not one at the end:
If the contract requires third-party inspection — SGS, Bureau Veritas, Intertek or your own QC — we arrange access and hold the shipment until the report is issued.
Finished pieces are crated in plywood cases with foam separation between faces, labelled by room and item number so the site team can unpack in the order they need. Flat-packed where the design allows, assembled where it does not.
Packing quality is usually where sea freight damage happens or does not. Corner protection and face separation matter more than the number of cartons.
Loaded FOB Shenzhen or Guangzhou, with the packing list, commercial invoice and any conformity documents issued in the format your customs broker needs. Container loading is photographed and the images sent before the vessel sails.
We do not install, but we stay available: installation drawings, missing-part replacement and fitting questions during the fit-out period are handled by the same contact who ran the order.
From a complete, approved package: 30 to 45 days to production complete, plus packing and shipping. Panel-only work runs faster than lacquered or veneered work; anything requiring imported hardware or stone adds lead time. The clock starts at step 5, not at step 1 — which is why the sample and specification steps deserve the attention they get.
To start at step 1, send your package through the contact page. To understand the specification decisions behind the manufacturing steps, the guides library covers boards, edge banding and contract-grade surfaces in detail.